We’re planning to replace the flat roofs with pitched roofs at Bowlas Avenue and Woodfield Close as part of our improvement works. We are finalising our planning application in readiness for submission over the coming weeks. This page includes key dates, updates, and links to help you stay informed throughout the process.

Bowlas Avenue drone footage

Project timeline and communications The table below sets out the key stages of the project, including when we’ll be in touch with important updates, opportunities for you to get involved, and when the work is expected to take place.

Milestone

Date

Notification of planning application letter

January 2026

S20 Notice of Intention with 30 day consultation period 

Early 2026

Customer Meeting (venue to be confirmed)

Early 2026 (in conjunction with S20 NOE)

Works begin on site 

April 2026

Works finish on site

March 2028

Invoicing 

January-March 2029

Project timeline and communications The table below sets out the key stages of the project, including when we’ll be in touch with important updates, opportunities for you to get involved, and when the work is expected to take place.

Date

January 2026

Date

Early 2026

Date

Early 2026 (in conjunction with S20 NOE)

Date

April 2026

Date

March 2028

Date

January-March 2029

If you have any comments that fall outside the formal consultation process, you can submit them using the form below.

Submit your comments