We’re planning to replace the flat roofs with pitched roofs at Bowlas Avenue and Woodfield Close as part of our improvement works. This page includes key dates, updates, and links to help you stay informed throughout the process.

Project timeline and communications The table below sets out the key stages of the project, including when we’ll be in touch with important updates, opportunities for you to get involved, and when the work is expected to take place.

Milestone

Date

Notification of planning application letter

May 2025

S20 Notice of Intention with 30 day consultation period 

July 2025

Customer Meeting (venue to be confirmed)

July-August 2025

S20 Notice of Proposal with 30 day consultation period 

October 2025

Works begin on site 

April 2026

Works finish on site

March 2028

Invoicing 

January-March 2029

Project timeline and communications The table below sets out the key stages of the project, including when we’ll be in touch with important updates, opportunities for you to get involved, and when the work is expected to take place.

Date

May 2025

Date

July 2025

Date

July-August 2025

Date

October 2025

Date

April 2026

Date

March 2028

Date

January-March 2029

If you have any comments that fall outside the formal consultation process, you can submit them using the form below.